Samarkand 1 & 2 Solar PV Projects – Phase II LALRP Surveys

About the Project

Title: Samarkand 1 & 2 Solar PV Projects – Phase II LALRP Surveys

Client: 5 Capitals / ACWA Power

Funding: ADB, EBRD, IFC, JBIC

Start date: (month/year): 10/2025

Completion date: (month/year): 2/2026

Regions: Uzbekistan | Samarkand Region

Energy

Land Acquisition and Livelihood Restoration Plan

Socio-Economic surveys

Compensation Packages

Grievance Redress Mechanism

Project Description

This project involves conducting Phase II Livelihood Acquisition and Livelihood Restoration Plan (LALRP) surveys for the interconnection facilities of the Samarkand 1 and 2 Solar PV projects in Uzbekistan.

The objective is to assess and value livelihood impacts for Project-Affected Households and Businesses (PAHs/PABs) along recently deviated OHTL route segments and at specific OHTL tower locations identified in the final detailed design. Key activities include conducting socio-economic surveys, asset inventory and valuation, disclosing compensation packages, and establishing a grievance redress mechanism.

Services Provided

01

Identify and survey any new Project-Affected Households/Businesses (PAHs/PABs) that were not previously recorded during Phase I.

02

Use provided Excel templates to collect data on each PAH/PAB, including names, land tenure type, land use, area of affected land, baseline income status, and socioeconomic vulnerability.

03

Conduct valuation surveys for all PAHs/PABs (both previously identified and newly found) affected by: i) Changed OHTL Route and Easement Corridor: Assessing temporary livelihood impacts during the construction period; ii) OHTL Tower/Pylon Sites: Assessing permanent livelihood impacts during and after construction.

04

Work with a licensed valuator to prepare official valuation reports for each PAP following national compensation standards.

05

Transfer key quantitative data from the valuator's reports into the provided Excel template for review.

06

Inform all project-affected communities and each PAH/PAB of the official cut-off date for the asset inventory survey. After this date, any new asset developments will not be eligible for compensation.

07

Disclose the compensation packages to the PAHs/PABs.

08

Collect comments and corrections from them, which will be used to revise the final compensation contract agreements between ACWA Power and the affected parties.

09

Introduce a new Grievance Redress Mechanism (GRM) specific to the Phase II LALRP process.