We are proud to announce the successful completion of the CAWRMP-ICW-01 (Lot 1) project stage focused on the modernization of the Jondor Main Canal and reconstruction of key structures along the Jondor Canal. This project is a critical component of the Climate Adaptive Water Resources Management in the Aral Sea Basin Sector Project in Bukhara region, Uzbekistan.
Project scope and achievements:
- Reconstruction of 35 hydraulic structures
- Construction of 41 new hydraulic structures
- Reconstruction of 5 road bridges
In total, 81 structures have been upgraded or newly built, boosting operational efficiency from 78% to 95–96%.
Importantly, the project was delivered with zero accidents, ensuring the highest standards of safety, environmental protection, and respect for local communities.