Feasibility Study for the Improvement of Tashkent Wastewater Treatment Facilities, Uzbekistan

About the Project

Title: Feasibility Study for the Improvement of Tashkent Wastewater Treatment Facilities, Uzbekistan

Client: SAMAN Corporation

Funding: Private

Start date: (month/year): 9/2021

Completion date: (month/year): 2/2022

Regions: Uzbekistan | Tashkent

Construction of Sewage Treatment Plant

Construction of Intercepting Sewer

Collection And Analysis of Basic Data and Current Status

Detailed Site Survey

Facility Plan

Review of PPP in Uzbekistan

Project Implementation Plan

Economic & Financial Feasibility Study

Project Description

Construction of sewage treatment plant (WWTP) and intercepting sewer in the southern part of the city of Tashkent, Uzbekistan.

  • Collection and analysis of basic data and current status of project area
  • Current status of existing sewage and wastewater treatment system
  • Detailed site survey (survey, ground investigation, water quality test)
  • Establishment of facility plan
  • Construction of Sewage treatment facility: A2O, Q: 250,000 m3/d
  • Construction of intercepting sewer: D500 ~ D1500, L = 17km ~ 19km
  • Review of PPP in Uzbekistan and project implementation plan
  • Economic & financial feasibility study

Services Provided

01

ESIA (Environmental and Social Impact Assessment)

02

Water Quality Analysis