Sarimay Solar PV Project Phase I: Lender’s Technical Advisor

About the Project

Title: Sarimay Solar PV Project Phase I: Lender’s Technical Advisor

Client: European Bank for Reconstruction and Development

Funding: European Bank for Reconstruction and Development

Start date: (month/year): 11/2023

Completion date: (month/year): 12/2023

Regions: Uzbekistan | Uch-Uchak village (Khorezm)

Site Assessment

Project Design Review

Technology Evaluation

Energy Yield Assessment

Grid Connection and Electrical Integration

Permitting & Regulatory Compliance

Review of Environmental and Social (E&S) Aspects

Risk Identification and Mitigation

Project Description

The main task is to provide an advisory for the Technical Due Diligence services to the EBRD for the financing of the 100 MW solar Photovoltaic (PV) plant project located near Uch-Uchak village, Uzbekistan.

Services Provided

01

Site visit and site conditions

02

Project stakeholders

03

Plant design

04

Grid connection

05

Project agreements

06

Permits and licenses